Substantial Completion: Construction Project Performance | Wennekers.Legal™
Helpful?
Yes No Share to Facebook

Substantial Completion:

Construction Project Performance



Last Updated: August 27 2026

Question: In Ontario, when is a construction or renovation project considered substantially complete for purposes of final payment and holdback?

Answer: In Ontario, a project is typically considered substantially complete when it is ready for use or being used for its intended purpose, and any remaining work is minor (often defect correction or final finishing touches) with the key definition set by the contract, while the Construction Act, R.S.O. 1990, c. C.30, at section 2 also provides a statutory test based on readiness for use and the allowable cost thresholds for known defects (  plus special rules where parties agree not to complete expeditiously).  Substantial completion matters for payment because the Construction Act requires holdbacks: after certification or declaration of substantial performance, an additional separate holdback of 10% applies to the remaining services or materials that will be supplied, and owners can face personal holdback liability to valid lien claimants under section 23, so any dispute about the milestone should be documented and reviewed against the contract terms.  If you need help assessing whether substantial completion has been achieved and how holdback and final payment should be handled for your project, reach out to Wennekers.Legal™ at (647) 701-1162 for professional legal services across Ontario.

Add this website to Google Preferred Sources


Understanding When Substantial Completion of a Construction or Renovation Project Will Likely Be Deemed As Achieved

Substantial Completion: Construction Project Performance Generally, substantial completion is an express term as negotiated between a project owner and a general contractor that sets out when a construction project will be deemed sufficiently completed with only minor work, such as defect corrections or what would be considered as final finishing touches remaining undone and outstanding.

Note: Please contact Wennekers.Legal™ by phone at: (647) 701-1162 to discuss any specific questions that you may have.

The Law

Although what will be deemed as the substantial completion milestone arises as a contractual term concern that may, generally, be freely negotiated between the project owner and the general contractor, the Construction Act, R.S.O. 1990, c C.30, also sets out conditions that apply to the determining of when, or if, substantial completion is achieved.  Specifically, the Construction Act states:


Contracts, substantial performance and completion

When contract substantially performed

2 (1) For the purposes of this Act, a contract is substantially performed,

(a) when the improvement to be made under that contract or a substantial part thereof is ready for use or is being used for the purposes intended; and

(b) when the improvement to be made under that contract is capable of completion or, where there is a known defect, correction, at a cost of not more than,

(i) 3 per cent of the first $1,000,000 of the contract price,

(ii) 2 per cent of the next $1,000,000 of the contract price, and

(iii) 1 per cent of the balance of the contract price.

Same

(2) For the purposes of this Act, where the improvement or a substantial part thereof is ready for use or is being used for the purposes intended and the owner and the contractor agree not to complete the improvement expeditiously, the price of the services or materials remaining to be supplied and required to complete the improvement shall be deducted from the contract price in determining substantial performance.

Adjudication amounts

(2.1) For the purposes of this Act, if an adjudicator makes a determination under Part II.1 in relation to a contract before the certification or declaration of the substantial performance of the contract under section 32,

(a) any amount determined by the adjudicator to be payable by a party to the contract shall be added to the contract price in determining substantial performance; and

(b) any amount determined by the adjudicator to have been overpaid by a party to the contract shall be deducted from the contract price in determining substantial performance.

Same

(2.2) Subsection (2.1) ceases to apply if,

(a) the adjudicator’s determination ceases to be binding on the parties to the adjudication under section 13.15; or

(b) the determination of the adjudicator is set aside on judicial review.

When contract deemed completed

(3) For the purposes of this Act, a contract shall be deemed to be completed and services or materials shall be deemed to be last supplied to the improvement when the price of completion, correction of a known defect or last supply is not more than the lesser of,

(a) 1 per cent of the contract price; and

(b) $5,000.

Multiple improvements under a contract

(4) If more than one improvement is to be made under a contract and each of the improvements is to lands that are not contiguous, then, if the contract so provides, each improvement is deemed for the purposes of this section to be under a separate contract.

When substantial completion is achieved and a Certificate of Substantial Completion is issued, legalities beyond the terms within the negotiated contract arise.  Beyond the substantial completion milestone, being the point at which the project is deemed usable or occupiable, the substantial completion milestone also sets the point at which final payment, minus statutory payment holdback, may become due and payable.  In regards to payment and holdback upon substantial completion, the Construction Act, R.S.O. 1990, c. C.30, states:


Holdbacks

Basic holdback

22 (1) Each payer upon a contract or subcontract under which a lien may arise shall retain a holdback equal to 10 per cent of the price of the services or materials as they are actually supplied under the contract or subcontract until all liens that may be claimed against the holdback have expired or been satisfied, discharged or otherwise provided for under this Act.

Separate holdback for finishing work

(2) Where the contract has been certified or declared to be substantially performed but services or materials remain to be supplied to complete the contract, the payer upon the contract, or a subcontract, under which a lien may arise shall retain, from the date certified or declared to be the date of substantial performance of the contract, a separate holdback equal to 10 per cent of the price of the remaining services or materials as they are actually supplied under the contract or subcontract, until all liens that may be claimed against the holdback have expired or been satisfied, discharged or otherwise provided for under this Act.

When obligation to retain applies

(3) The obligation to retain the holdbacks under subsections (1) and (2) applies irrespective of whether the contract or subcontract provides for partial payments or payment on completion.

Permissible forms of holdback

(4) Some or all of any holdbacks may, instead of being retained in the form of funds, be retained in one or more of the following forms:

1. A letter of credit in the prescribed form.

2. A demand-worded holdback repayment bond in the prescribed form.

3. Any other form that may be prescribed.

Personal liability

23 (1) Subject to subsections (2), (3) and (4), an owner is personally liable for holdbacks that the owner is required to retain under this Part to those lien claimants who have valid liens against the owner’s interest in the premises.

Limitation

(2) Where the defaulting payer is the contractor, the owner’s personal liability to a lien claimant or to a class of lien claimants as defined by section 79 does not exceed the holdbacks the owner is required to retain.

Same

(3) Where the defaulting payer is a subcontractor, the owner’s personal liability to a lien claimant or to a class of lien claimants as defined by section 79 does not exceed the lesser of,

(a) the holdbacks the owner is required to retain; and

(b) the holdbacks required to be retained by the contractor or a subcontractor from the lien claimant’s defaulting payer.

How determined

(4) The personal liability of an owner under this section may only be determined by an action under this Act.

Conclusion

In determining whether substantial completion is achieved, it is important to consider both the physical state of the project and the contractual obligations between the parties.  Substantial completion generally means that the project is sufficiently finished, allowing use of the project for the intended purpose, even if minor deficiencies remain.  Courts will consider factors such as the remaining work, the impact on usability, and the reasonable expectations of the parties.  Proper documentation, clear communication, and attention to the specifics of contractual definitions will help to ensure that disputes regarding substantial completion are minimized.

9

NOTE: A significant number of online searches for “lawyers near me” or “best lawyer in” typically indicate a demand for prompt, skilled legal support rather than a specific occupation title.  In Ontario, certified paralegals are governed by the same Law Society that regulates lawyers, granting them the authority to represent clients in specific legal matters.  Core activities in that capacity include advocacy, legal evaluation, and procedural expertise.  Wennekers.Legal™ provides legal representation within its licensed framework, focusing on strategic planning, evidence preparation, and effective advocacy aimed at securing timely and favourable outcomes for clients.

AR, BN, CA+|EN, DT, ES, FA, FR, GU, HE, HI
IT, KO, PA, PT, RU, TA, TL, UK, UR, VI, ZH
Send a Message to: Wennekers.Legal™

NOTE: Do not send confidential details about your case.  Using this website does not establish a legal-representative/client relationship.  Use the website for your introduction with Wennekers.Legal™. 
Privacy Policy & Cookies | Terms of Use Your IP Address is: 216.73.216.186

Application Hosted on Microsoft Azure Cloud Web Servers | Analytics by Google
Let’s Encrypt SSL certificate is a service provided by the Internet Security Research Group (ISRG)
All names, trademarks and/or logos are those of their respective owners.

This webpage was served on: September 12 2026 at 07:57:33PM Eastern.

.




Assistive Controls:  |   |  A A A